2023 Capital Projects
2023 Paving Construction
Hordal Road Phase 2
Project Area: Hordal Road from Spence Road to Finlayson Drive
Start/Finish: Mid July – Early September
Contractor: ACE Enterprises Ltd.
Description: The project will include reinstatement of all asphalt, curb and sidewalk removed during last year’s Water and Sewer Upgrade.
Wiley Road
Project Area: Wiley Road
Start/Finish: Mid May – Late June
Contractor: ACE Enterprises Ltd.
Description: The project will include full replacement of all paved surfaces as well as curb and sidewalk.
Franklin
Project Area: Franklin from Weaver to Bretzlaff Drive
Start/Finish: Mid June – Early August
Contractor: ACE Enterprises Ltd.
Description: The project will include full replacement of all paved surfaces as well as curb and sidewalk.
50th Street
Project Area: 50th Street
Start/Finish: Late May – Early August
Contractor: NWT Construction Ltd.
Description: The project will include full replacement of all paved surfaces as well as curb and sidewalk.
Kam Lake Road and Deh Cho Boulevard
Project Area: Kam Lake Road and Deh Cho Boulevard
Start/Finish: Late July – Early September
Contractor: NWT Construction Ltd.
Description: The project will include full replacement of all paved surfaces as well as curb and multi-use path.
Aquatic Centre
Franklin Avenue Closure (adjacent to Aquatic Centre) Phase 1
Project Area: South East side of Franklin Avenue closed
Start/Finish: June 12 - early July
Contractor: Clark Builders
Description: All traffic on Franklin Ave. throughout Phase 1 will be diverted to the utilize the NW side of the road to allow north eastbound and south westbound traffic to continue at the reduced speed limit. Left hand turns will not be allowed at any point throughout the construction zone.
No access to Forrest Drive from Franklin Ave. is permitted from either direction. Traffic lights at the Franklin Ave. and Forrest Drive Intersection to be disabled as general traffic will be allowed to flow.
Forrest Drive will be limited to local traffic only West of Taylor road as access to Franklin Ave. will be closed during this time. The sidewalk across Forrest Drive at Franklin Ave. will also be closed due to the proximity to construction
Franklin Avenue Closure (adjacent to Aquatic Centre) Phase 2
Project Area: North West side of Franklin Avenue closed
Start/Finish: Early July - late July
Contractor: Clark Builders
Description: All traffic on Franklin Ave. throughout Phase 2 will be diverted to the utilize the SE side of the road to allow north eastbound and south westbound traffic to continue at the reduced speed limit. Left hand turns will not be allowed at any point throughout the construction zone.
No access to Forrest Drive from Franklin Ave. is permitted from either direction. Traffic lights at the Franklin Ave. and Forrest Drive Intersection to be disabled as general traffic will be allowed to flow.
Forrest Drive will be limited to local traffic only West of Taylor road as access to Franklin Ave. will be closed during this time. The sidewalk across Forrest Drive at Franklin Ave. will also be closed due to the proximity to construction.